Get our free email newsletter

New Voltage Sag Testing Requirements for Industrial Equipment

Power Quality Monitoring is Migrating to the Product Level

Immunity from voltage sags is vital for reliable operation of our ever-more-sophisticated electronic controls and equipment. Every electrical product should be able to ride through typical voltage sags, but in many cases the first sag test occurs after equipment is installed and in operation. Select the appropriate sag immunity specification and equipment compliance testing, and you’ll be glad you did.

Modern equipment can be sensitive to brief disturbances on utility power mains. Electrical systems are subject to a wide variety of power quality problems that can interrupt production processes, affect sensitive equipment, and cause downtime, scrap, and capacity losses. The most common disturbance in the process industry, by far, is a sag, that is, a brief reduction in voltage lasting a few hundred milliseconds.

- Partner Content -

A Dash of Maxwell’s: A Maxwell’s Equations Primer – Part One

Solving Maxwell’s Equations for real-life situations, like predicting the RF emissions from a cell tower, requires more mathematical horsepower than any individual mind can muster. These equations don’t give the scientist or engineer just insight, they are literally the answer to everything RF.

Sags are commonly caused by fuse or breaker operation, motor starting or capacitor switching, but they are also triggered by short circuits on the power distribution system caused by events such as snakes slithering across insulators, trenching machines hitting underground cables, and lightning ionizing the air around high-voltage lines. Many utilities report that 80 percent of electrical disturbances originate within the user’s facility.

A decade ago, the solution to voltage sags was to try to fix them by somehow storing enough energy and releasing it onto the AC mains when voltage dropped. Some of the old solutions included an uninterruptible power supply (UPS), flywheels, and ferroresonant transformers.

More recently, engineers have realized that voltage sag is really a compatibility problem with at least two classes of solutions. Either you can improve the power or you can make the equipment tougher. The latter approach is called “voltage sag immunity,” and gets more important around the world.

1207 F3 fig1
Figure 1: Immunize your products and facilities. Voltage sag immunity testing has been common in the semiconductor industry for years and has proved its economic value. New IEC standards for voltage sag immunity will expand this kind of testing and certification to other industries.

Standards Developed

Three main primary voltage sag immunity standards are IEC 61000-4-11, IEC 61000-4-34, and SEMI F47. There are other standards in use, such as IEEE 1100, CBEMA, ITIC, Samsung Power Vaccine, international standards, and MIL-STD. But the first three seem to have the widest acceptance in the marketplace. (IEC is the International Electrotechnical Commission, SEMI is the Semiconductor Equipment and Materials Institute, CBEMA is the Computer Business Equipment Manufacturers Association, ITIC is the Information Technology Institute Council, and MIL-STD is the U.S. Defense Department’s specification.)

- From Our Sponsors -

IEC 61000-4-11 and the very new IEC 61000-4-34 are a closely related set of standards that cover voltage sag immunity. IEC 61000-4-11 Ed. 2 covers equipment rated at 16 amps per phase or less while IEC 61000-4-34 Ed. 1 covers equipment rated at more than 16 amps per phase. The latter was written after IEC 61000-4-11, so it seems to be more comprehensive. IEC 61000-4-34 also might become a harmonized EN standard later in 2015 or in early 2016.

SEMI F47 is the voltage sag immunity standard used in the semiconductor manufacturing industry, where a single voltage sag can result in the multi-million dollar loss of product if a facility is not properly protected. The semiconductor industry has developed specifications for its manufacturing equipment and for components and subsystems in that equipment. Enforcement is entirely customer-driven in this industry, as semiconductor manufacturers understand the economic consequences of sag-induced failures and generally refuse to purchase new equipment that fails the SEMI F47 immunity requirement. SEMI F47 is currently going through its five-year revision and update cycle.

All three standards specify voltage sags with certain depths and durations for the equipment under test (EUT). For example, a specification may state 70 percent of nominal for 500 milliseconds. The percentage is the amount of voltage remaining, not the amount that is missing. Each standard specifies pass-fail criteria for an EUT when a voltage sag is applied. The IEC standards have a range of pass-fail criteria, but the SEMI F47 standard is more explicit (see Figure 2).

1207 F3 fig2
Figure 2: Playing through. A typical example of a voltage sag ride-through curve compared with the SEMI F47 specification commonly used in the semiconductor industry.

Three-Phase Testing

For three-phase EUTs, the sags are applied between each pair of power conductors, one pair at a time. If there is a neutral conductor, this implies that there are six different sags at each depth-duration pair, that is, three different phase-to-phase sags, and three different phase-to-neutral sags. If there is no neutral conductor, there are just three different sags at each depth-duration pair in the standard, just three different phase-to-phase sags. In all of the standards, all three phases are never sagged at the same time.

Note that IEC 61000-4-11 and 61000-4-34 specifically forbid creating phase-to-phase sags by sagging two phase-to-neutral voltages simultaneously, an approach that is permitted in SEMI F47. Instead, you must create phase shifts during your phase-to-phase sags, something that sag generators that have been designed for these standards do automatically.

1207 F3 fig3
Figure 3: The IEC standards require phase shifting during sags on three-phase systems, but sags on all three phases simultaneously are not required.

What Makes Voltage Sag Testing Different

In contrast to most other emissions and immunity testing, voltage sag testing requires the engineer to control and manipulate all of the power flowing into an EUT. For smaller devices such as personal computers, this is not a great challenge. But for larger industrial equipment, perhaps rated at 480 volts three-phase at 200 amps per phase, with an expected inrush current of 600 amps or more, the test engineer must be prepared for serious performance and safety challenges.

A voltage sag generator is a piece of test equipment that is inserted between the AC mains and the EUT. It generates voltage sags of any required depth and duration. Some voltage sag generators include pre-programmed sags for each of the IEC, SEMI or MIL standards.   

Because a common EUT failure mechanism is a blown fuse or circuit breaker during the current inrush after a voltage sag, the sag generator must be specified for delivering large peak currents, typically in the hundreds of amps. This peak current requirement in the IEC standards means that electronic amplifier AC sources generally can only be used for pre-compliance testing, and not for certification.

1207 F3 fig4
Figure 4: The voltage sag test engineer will insert a sag generator between the AC source and the equipment under test. Often, high currents (200 amps) and high voltages (480 volts 3-phase) must be handled.

Certain sag immunity testing software comes with extensive safety checklists. Some of the checklist items are obvious (such as “Who on the test team is trained in CPR?” or “Where is the closest fire extinguisher?”) and some are less obvious (for example, “How do we get access to at least two upstream circuit breakers?” or “Where is the closest trash can?”).

This kind of testing requires a fully-functional EUT as well as someone who knows how to operate it.  he only way to determine if an EUT is immune to the required voltage sags is to have it fully operating during voltage sag testing. In many cases, the sags will need to be applied during different stages of EUT operation. Remarkably often, an EUT is not ready on time for voltage sag testing. Development work may need to be completed, or no one is available to operate the EUT, or the supplies to operate the EUT (raw materials, cooling water, compressed air, etc.) are not available, or the EUT software is broken. Test engineers should plan for these kinds of problems.

EUT failure mechanisms can be complicated, too, and a test engineer will be expected to help diagnose them. The built-in digital oscilloscopes in most sag generators will help, but a test engineer must figure out where to connect the channels to circuits inside an EUT.

Common Failure Mechanisms Due to Voltage Sags

The most common failure mechanism is lack of energy. This can manifest itself in something as simple as insufficient voltage to keep a critical relay or contactor energized, or something as complex as an electronic sensor with a failing power supply giving an incorrect reading, which would cause EUT software to react inappropriately (see Figure 5).

1207 F3 fig5
Figure 5: Anatomy of voltage sag. To test a new product, a voltage sag is introduced in the power source (a). The waveform, which was about 40 amps peak before the sag in this example, then increases to 450 amps peak after the voltage sag (b). The same current, this time expressed as an RMS value, is shown. The next graph shows the same current, this time as an RMS value. Before the sag, it was about 23 amps RMS (this equipment was rated at 30 amps), but after the sag the current increased to 175 amps RMS. This behavior is not unusual (c). The final graph shows the output of a DC supply during this sag (d).

The second most common failure mechanism, surprisingly, occurs just after the sag has finished. In such cases, all of the bulk capacitors inside an EUT recharge at once, causing a large increase in AC mains current. This increase can trip circuit breakers, open fuses, and even destroy solid-state rectifiers. Most design engineers correctly protect against this inrush current during power cycling, but many do not consider the similar effects of voltage sags. Be careful when the test procedure is developed. If you use a sag generator that lacks sufficient current capability, it will incorrectly pass the equipment if there is insufficient current available to blow a fuse or trip a circuit breaker in a half-cycle.

Another common EUT failure mechanism occurs when a sensor detects the voltage sag and decides to shut down the EUT. In a straightforward example, a three-phase EUT might have a phase-rotation relay that incorrectly interprets an unbalanced voltage sag as a phase reversal and therefore shuts down the EUT. A more atypical example would be if you had an airflow sensor mounted near a fan, it detected that the fan had slowed down momentarily, and the equipment software misinterpreted the message from this sensor as indicating that the EUT cooling system had failed. In this case, a software fan failure signal delay is the solution to improve sag immunity.

One more typical EUT failure mechanism involves an uncommon sequence of events. For example, in one case, a voltage sag was applied to the EUT and its main contactor opened with a bang. But further investigation revealed that a small relay, wired in series with the main contactor coil, actually opened because it received an open relay contact from a stray water sensor. That sensor, in turn, opened because its small 24-VDC supply output dropped to 18 V during the sag. The solution was an inexpensive bulk capacitor across the 24-VDC supply.

Many other failure mechanisms can take place during voltage sags. The question to the test engineer will always be “How do we fix this problem?” Usually, there is a simple, low-cost fix once the problem is identified.

A New Embedded Power Quality Measurement Technology

There is a new way to increase the reliability of products due to common power quality and voltage sag problems. How about making the product more intelligent, so it can react depending on severity of the voltage sag problem? Until recently, power quality monitors have been used exclusively at the facility level, and are much too big and too expensive to design and integrate into products. However, a new generation of smaller power quality monitors are available that facilitate the trend toward embedded, intelligent power quality functionality.

You will see more and more of such permanently installed power quality monitors on a product level. This new embedded technology comes with the huge advantage that power quality problems and energy consumption can be evaluated directly within the product or machine.

Conclusion

With the ever-increasing use of sophisticated controls and equipment in industrial, commercial, institutional, and governmental facilities, the continuity, reliability, and quality of electrical service has become extremely crucial to many power users. The power hardly gets better in the future, so the ultimate goal for any product manufacturer is to make its product immune to voltage sags. Just as all modern cars should be able to drive through regular bumps on the road, every electrical product should be able to ride through any regular voltage sags that will occur, regardless of the power that a facility can provide.

References

  1. IEC 61000-4-34, Ed 1, “Testing and measurement techniques –Voltage dips, short interruptions and voltage variations immunity tests for equipment with input current more than 16A per phase”. International Electrotechnical Commission. October 2005.
  2. SEMI F47-0706, “Specification for Semiconductor Processing Equipment Voltage Sag immunity”. June 2007.
  3. IEC 61000-4-30, Ed 2, “Testing and measurement techniques – Power Quality Measurement Methods”. International Electrotechnical Commission. October 2008.
  4. Handbook of Power Signatures, Alex McEachern, 1989

author eberhard-andreasAndreas Eberhard is member of various power quality standard committees around the world. He is involved in IEC 61000-4-34, SEMI F47 and IEEE standard committees, and has over 15 years of experience in product compliance based on international standards. He is Vice-President of Technical Services at PSL – Power Sensors Ltd.  and can be contacted at aeberhard@powerstandards.com, or by phone at (510) 522-4400.

Related Articles

Digital Sponsors

Become a Sponsor

Discover new products, review technical whitepapers, read the latest compliance news, trending engineering news, and weekly recall alerts.

Get our email updates

What's New

- From Our Sponsors -

Sign up for the In Compliance Email Newsletter

Discover new products, review technical whitepapers, read the latest compliance news, trending engineering news, and weekly recall alerts.